Set up an approval workflow

Decide who must approve one kind of document, in what order, and for what value. The usual case takes three actions: add a step, choose the approvers, save.

  • You need the “Manage approval workflows” permission. Administrators always have it. Nobody else has it until an administrator ticks it for them under Users.
  • Approvers are chosen by name, so the people must already be users.
  1. Open the grid of tiles in the top bar and choose Approval workflows, next to AI credits. The screen has a panel for each kind of document.
  2. In the panel for the kind you want, choose Set up workflow.
  3. Used on: leave All projects, or choose One project and find the project by name. A project with its own workflow follows it instead of the one for all projects.
  4. In Step 1, give the step a name, such as “Project manager”. If you leave it empty it is called Step 1.
  5. Under Approvers, choose Add a person. Add more with Add another.
  6. If the step has more than one person, choose Any one of them approves or All of them must approve.
  7. Applies to: leave Every value, or choose A value range and type the values, ex GST. Leave the first box empty for “from any value” and the second empty for “no limit”.
  8. For a second approver, choose Add a step and repeat. Steps are asked in turn: the next starts when the one before has approved. Use the arrows to change the order.
  9. If any step has a value range, Check a value appears. Type a value to see who would be asked to approve it.
  10. Choose Save.
  1. On the step, switch on Remind if it waits.
  2. Type the number of days in Remind after: 3 unless you change it, and at most 60. The people on the step get the notice again once it has waited that long.
  3. Optionally, in Then also ask, choose one more person. If it is still waiting the same number of days after the reminder, that person is added to the step and can approve it on their own, even on a step where all must approve.

The workflow’s panel shows the reminder under the step, for example “Reminder after 3 days, then also Sam Nguyen”.

  • Edit beside a workflow opens it again.
  • The Status switch turns a workflow Off without deleting it. While it is off, that kind of document is approved in one step by anyone with the approve permission.
  • Delete is at the bottom left of the window and asks first.
  • To give one project different steps once the company has a workflow, choose Use different steps on one project in the same panel.
  • If documents are already waiting when you save, a Saved window says how many. They keep the steps they were sent with. To put one through the new steps, open it, choose Take it back, then send it for approval again. Nothing is moved for you.
  • A value range runs from the first value up to, but not including, the second. “From $10,000 to under $50,000” covers $10,000 and does not cover $50,000. Set the next step to start at $50,000 so no value falls between two steps.
  • A step whose range does not cover the document’s value is skipped.
  • If no step covers a value, the document does not go through the workflow. Check a value tells you when this would happen.
  • Changing or deleting a workflow does not change requests already waiting. They keep the steps they started with.
  • Reminders go out overnight, once. A request already waiting when you add a reminder is not reminded.
  • The person you also ask cannot already be on the step, and is not added if they sent the document themselves.
  • A kind of document has one workflow for all projects, and at most one for each project. A project that already has its own is shown greyed in the project list.
  • A step shows “Nobody to approve” if everyone on it has left. Edit the workflow and add someone.
  • Approvers are people in your own company. Clients, superintendents and consultants cannot be approvers.