Record an extension of time

When the work is held up and you claim more time from the client, record the claim in the extensions of time register, then record what the client answered. The days the client approves move the date for practical completion.

  • Who can do this: anyone with Manage extensions of time and delay notices, for the whole company or through their role on the project. Administrators always can.
  • To put approved days on the programme, you also need the Schedule permission Add Delay.
  1. Open Head Contract and the Extensions of time tab. Across the top are the days approved, the days waiting for the client and the date for practical completion.
  2. If you gave the client a delay notice from the Schedule, it is listed under Delay notices not in the register. Choose Add to the register on it: the cause, the day it was given and the days claimed are read from the notice. Go on to step 7.
  3. Otherwise choose Record an extension claim.
  4. Type the Cause, such as “Wet weather, 3 to 7 March”, and choose the day it was Given to the client.
  5. Type the Days claimed. They are working or calendar days, as the contract sets.
  6. If the letter you sent is in Correspondence, choose Add a letter under Notice it came from and pick it. Then choose Record extension claim. The claim gets the next number, such as EOT-003, and shows Waiting for the client.
  7. When the client answers, choose Record answer on the claim.
  8. Under The client, choose Approved or Rejected. For Approved, type the Days approved. Choose the day it was Answered on, and type the Client’s reference or the Reason given if you have one.
  9. Read the sentence at the bottom, for example “The date for practical completion moves out by 4 working days, 2 fewer than claimed.” Then choose Save.
  • The date for practical completion moves by the days approved, on this tab and across the top of the page. A claim approved for fewer days than claimed shows Approved in part.
  • On an approved claim, Add to the programme puts the days on the Schedule as a delay. Choose the Task that was held up (and the Estimate first, if the project has more than one programme). The window says when the programme finishes now and when it would finish with the delay. Nothing changes until you choose the button, such as Add 4 working days to the programme.
  • The claim then says “On the programme: 4 days on …” with the task’s name. Choose it to see what was added, or to Take it off the programme.
  • The client cannot approve more days than were claimed. The form refuses it.
  • An answered claim cannot be edited. Choose Change answer, set it to Still waiting, edit it, then record the answer again.
  • If you change the days approved, or reject a claim, while its delay is on the programme, you must choose Take it off the programme or Leave it on the programme before saving.
  • A claim with a delay on the programme cannot be deleted until the delay is taken off.
  • A delay on the programme makes the task longer by that many working days, as for any delay added in the Schedule. Tasks linked after it move with it.
  • A deleted claim’s number is not used again.