Record a hazard or good practice
When you see a hazard on site, record it, give it to someone to fix, and close it out when it is dealt with. Good practice worth noting is recorded the same way and needs nothing more.
Before you start
Section titled “Before you start”- Who can do this: “Record incidents and observations”. Administrators always can.
- The person a hazard is given to can close it out without that permission.
- Open Safety and choose the Observations tab.
- Choose Record an observation.
- Kind: Hazard or Good practice.
- What was seen: describe it, for example “Open penetration in the Level 5 slab with no cover”.
- Location and Where exactly, if you want to say where.
- For a hazard only: choose who it is Assigned to and set the Due date. Both are optional.
- Add a Photo if you have one.
- Choose Record observation. It is listed with its number, for example OBS-007. A hazard shows Open; a good practice shows Noted.
To close out a hazard:
- Click its row on the Observations tab.
- Type What was done about it.
- Choose Close out. It shows Closed out, and the open hazards figure at the top goes down by one.
Good to know
Section titled “Good to know”- A good practice is never open. Choose All to see it in the list.
- A hazard past its due date shows Overdue, and counts in the overdue figure at the top.
- A closed-out hazard can be opened again with Reopen.
- If the photo fails to upload, the observation is still recorded; add the photo again from the observation.
- Nothing here sends a notice to the person a hazard is assigned to. Tell them.