Head Contract

Head Contract holds the contract with the client: what it is worth, how that is broken down, the retention the client holds, and the date the work must be finished by. It also keeps the register of extensions of time, so the date for practical completion moves when the client approves more time.

Claims to the client are still made in Progress Claims. Head Contract sets up what those claims are made against.

It is in the menu on the left, under Contracts, and works on the project chosen in the left-hand picker.

Across the top, every figure is worked out for you:

  • Contract sum, ex GST.
  • Schedule of values, and whether it matches the contract sum or how far it is short of it.
  • Retention on each claim, and the most the client can hold.
  • Date for practical completion, moved by the extensions of time approved so far. If the date has passed, it says how many days late and what that is in liquidated damages.

Under the figures are three tabs: Contract, Schedule of values and Extensions of time.

Word Meaning
Contract sum What the contract with the client is worth, ex GST
Schedule of values The lines the contract sum is broken into, as the contract lists them. Claims can be made against these lines
Retention Money the client holds back from each claim, up to a limit, and hands back at practical completion and at the end of the defects period
Date for practical completion The date in the contract. The page also shows it moved by approved extensions of time
Extension of time A claim to the client for more time, numbered EOT-001, EOT-002 and so on
Delay notice A notice given to the client from the Schedule. One that claims days can be put in the extensions of time register with one press
Liquidated damages An amount for each day the work is late, if the contract has one
Opening balance For a job already under way: what had been claimed and the retention the client held before the project came into SmarteBuild
  1. Set up the head contract
  2. Enter the schedule of values
  3. Record an extension of time
  4. Make a claim against the schedule of values