Enter the schedule of values

The schedule of values is the list of lines the contract sum is made of, in the contract’s own order. Each month’s claim against the schedule is made line by line, so enter it once, as the contract has it, before the first claim.

  • Who can do this: anyone with Set up the head contract and schedule of values, for the whole company or through their role on the project. Administrators always can.
  • The contract is set up on the Contract tab, so the schedule can be checked against the contract sum.
  1. Open Head Contract and the Schedule of values tab.
  2. Choose Add a line.
  3. Type the Item number as the contract numbers it, such as 3.2. It is optional.
  4. Type the Description, such as “Concrete structure”.
  5. If the project has buildings and levels, choose a Location for a line the contract breaks down by building or level. Leave it as the whole project otherwise.
  6. Type the Amount, ex GST.
  7. Choose Add and enter another to save this line and start the next one with the cursor back in the Item box. Choose Add line for the last one.
  8. Read the line above the list. It says either “The schedule adds up to the contract sum of …” or how much the schedule is short of, or more than, the contract sum.
  • When lines are put on buildings, a By building list under the schedule gives the total for each.
  • Once the schedule adds up to the contract sum, claims can be made against it in Progress Claims: see Make a claim against the schedule of values.
  • Once a claim against the schedule is approved, its amounts are fixed. The amounts, new lines, deleting a line and the contract sum are then refused. Wording, item numbers, locations and the order can still be corrected. Changes to the contract sum come through client variations.
  • A claim cannot be started until the schedule adds up to the contract sum.
  • Each line has Move up, Move down, Edit and Delete buttons, so the schedule can be put in the contract’s order.
  • A schedule holds up to 1,000 lines.