Set up the inspection plan for a project
The plan says, for each trade, which checklist it is inspected with and how often: each unit, each level, each building or once. Set it up before the trades start, and the grid shows from day one what has to be inspected and where.
Before you start
Section titled “Before you start”- Who can do this: anyone with “Set up inspection plans” on the project. Administrators hold it. Without it you can read the plan but not change it.
- The project’s buildings, levels and units are set up in Buildings & Units. The plan works out the inspections from them.
- The checklists you want to use exist under Templates, with their hold points marked.
- Open Quality, choose the project on the left, then the ITPs tab.
- Press Plan. On a project with no plan yet, press Set up the plan instead.
- Press Add a trade. The window Add a trade to the plan opens.
- Trade: type the trade or the work, for example Waterproofing. Common trades are offered as you type.
- Checklist: choose the template it is inspected with. The line under it says how many hold points it has.
- How often: choose Each unit, Each level, Each building or Once. The line under it says what that needs, for example “40 inspections: one for each unit.”
- Holds up (optional): the programme task that waits for these inspections, for example Tiling Level 2.
- Done by (optional): the subcontract for this trade.
- Press Add to plan. The trade is listed with its checklist, how often and how many inspections it needs.
- Repeat for each trade, then press Progress to see the grid.
What happens next
Section titled “What happens next”The grid shows one row for the trade, with a cell on each level where it needs inspecting. Nothing is stored for an inspection until someone starts it.
Good to know
Section titled “Good to know”- Adding a level or a unit in Buildings & Units adds its inspections straight away. You do not change the plan.
- To change a trade, press Change on its line. Inspections already started stay where their places still match.
- Remove is in the same window. It asks first; inspections already done for the trade stay in Checklists but no longer show in the grid.
- Holds up offers the tasks of the estimate open on the page. When a hold point is waiting on that trade, the ITPs list it with how many days until the task starts.
- Holds up and Done by appear only when there is something to choose.
- Areas such as a plant room are not inspected per unit or per level. Use Once for work done there.

