Add a subcontract variation
Once a subcontract is approved, any change to its price is a variation: extra work, or work taken out. When a variation is approved, the contract value and the purchase order move by the same amount, so the committed cost always agrees with the subcontract.
Before you start
Section titled “Before you start”- You need the “Create and edit subcontract variations” permission.
- The subcontract is Approved, Out for signing or Executed.
- Open the subcontract and the Variations tab. Choose Add a variation.
- Type a Title, such as “Acoustic tiles, Level 5 lobby”.
- Under Kind, choose Addition or Deduction, and type the Amount ex GST.
- Choose the Cost code. It is the cost code of the line added to the purchase order.
- Choose a Location if the change is in one place, such as Unit 501.
- Under Paid for by, choose the client variation that pays for it, if there is one.
- Read the line underneath. It says what the contract value becomes and how much the purchase order rises or falls.
- Choose Add variation. It is listed as a Draft with its number, such as SCV-003.
- Choose Send for approval on its row. Where no approval workflow applies, someone with the “Approve subcontracts and subcontract variations” permission sees Approve instead, then Approve variation.
What happens next
Section titled “What happens next”When it is approved, a line for it is added to the schedule (marked Variation) and to the purchase order, and the revised contract value changes. If you chose a client variation, that client variation now shows its subcontract cost and the margin left, on the Client variations tab of the list and in Variations.
Good to know
Section titled “Good to know”- An approved variation cannot be changed or deleted. To correct one, add another the other way.
- A deduction goes through the approval workflow by its size: a $20,000 deduction is approved as $20,000.
- A Draft or rejected variation can be changed with the pencil, or deleted with the bin. Its number is not used again.
- If the purchase order is still waiting for approval in Orders when a variation is approved, the order’s approval starts again at the new value. The question before you approve says so.