Make a subcontract
Once a trade’s quote is awarded, or its purchase order is raised, make the subcontract from it. The subcontractor and the sum come across from the order, so nobody types them again. Then set the terms and check the schedule before it goes for approval.
Before you start
Section titled “Before you start”- You need the “Create and edit subcontracts” permission. To make one from a quote, you must also hold the Orders permission Generate a new order.
- The quote is awarded in Tenders, or the purchase order exists in Orders. Each order can have only one subcontract.
Make it
Section titled “Make it”- Open Subcontracts and choose New subcontract.
- Under Made from, choose An awarded quote or A purchase order. Each lists the subcontractor and the value of what is available.
- Pick one. The line underneath says what will happen, for example “A draft subcontract with Dryline Interiors for $1,322,000 ex GST.”
- Choose Create subcontract. It opens as a Draft, on its Summary tab.
Set the terms
Section titled “Set the terms”- On the Summary tab, under Terms, choose Edit terms.
- Fill in what applies: Scope of works, Start and Completion, Retention, Retention limit and Released at completion (all percentages), Defects period in months, Payment terms in days and Claim day of the month.
- Under For the printed agreement, choose the Agreement template. It fills in the margins, interest, liquidated damages, who insures the works and how often claims are made; change any that differ for this trade.
- Choose Save. The Summary now says the retention in words, such as how much is held from each claim and when it is released.
Check the schedule
Section titled “Check the schedule”- Open the Schedule tab. It starts as a copy of the order’s lines, and the line at the top says whether it agrees with the contract sum.
- To change it, choose Edit schedule. Each line has a Description, Cost code, Unit, quantity, Rate and Amount, and a Location when the project has buildings set up.
- Choose Save schedule. The top line says whether it now agrees, or by how much it is out.
Good to know
Section titled “Good to know”- The schedule must add up to the contract sum before the subcontract can be sent for approval. Change the lines, or change the order in Orders.
- A line with a quantity and a rate has its amount worked out for you. Leave both empty to type a lump sum.
- Copy from the purchase order again in the schedule window replaces the schedule with the order’s lines.
- Generate from a template on the Schedule tab writes a schedule by unit, level or block from one of your company’s schedule templates. Lines added by hand are kept if you generate again.
- If the head contract has a practical completion date, a new subcontract’s Completion starts on it.
- Terms and schedule can be changed only while the subcontract is a Draft. After that, a change in money is a variation.
- Delete this draft removes the subcontract and its schedule; the purchase order stays. You need the “Delete subcontracts” permission.