Workforce Planning
Workforce Planning is where you plan your own people: who is on which project each week, who is free, who is double-booked, and how many of each trade each project needs against who is available. It also keeps each person’s tickets and licences with their expiry dates.
It covers the whole company, not one project, so it does not use the project in the left-hand picker. Open Workforce Planning from the menu on the left.
The tabs
Section titled “The tabs”- Board: people down the side, eight weeks across. Each week shows the project or projects the person is on, or Free.
- Demand: how many people of each trade or role each project needs, week by week, with who is assigned underneath.
- Next month: next month’s need for the whole company and for each project, against who is free.
- Planned and actual: the days planned on the Board against approved timesheet hours.
- People: the list of people, their trade or role, crew, and tickets.
- Crews and roles: crews, and the company’s list of trades and roles.
The words used
Section titled “The words used”| Word | Meaning |
|---|---|
| Person | Someone you plan. Either someone who logs in to SmarteBuild, or a name only, for people who do not |
| Trade or role | What a person does: Carpenter, Labourer, Site Manager. One for each person |
| Crew | People usually sent to a job together. A person is in one crew at most |
| Ticket | A ticket or licence, such as a White Card, with an optional number and expiry date |
| Assignment | A person on a project from a first week for so many weeks, full time or part of their time |
| Free, part free | Nothing assigned that week, or less than their whole week |
| Double-booked | Assigned more than their whole week. It can be saved, and the Board marks it |
| Need | So many people of one trade or role on one project in one week. Halves are allowed |
| Short | Fewer people assigned than needed |
Weeks run Monday to Sunday, the same as Timesheets. Planning is in whole weeks.