Quality

Quality is where the job’s inspections are planned, done and kept. The inspection and test plan says which checklist each trade is inspected with, and whether that is done for each unit, each level, each building or once for the project. The grid then shows which levels each trade has passed, and the register for a trade can be printed for the certifier or the client.

Open Quality from the menu on the left and choose the project on the left. The page has three tabs:

  • ITPs: the inspection and test plans. It has three views, chosen with the buttons on the right: Progress (the grid), Plan and Register.
  • Checklists: every checklist on the job, whether it was started from the ITPs or on its own. The number on the tab is how many are still open.
  • Templates: the blank checklists. The SmarteBuild starters can be used as they are or copied and changed; your own can carry hold and witness points.

The page opens on the tab you used last.

Word Meaning
ITP An inspection and test plan: for each trade, the checklist used and how often it is done
Template A blank checklist. A change to a template never changes a checklist already started from it
Checklist One inspection, filled in: each item answered Pass, Fail or N/A, with notes, photos and signatures
Hold point An item where work stops until a named person releases it. The checklist cannot be completed until it is released
Witness point An item someone may be asked to witness. Who witnessed it can be recorded; it never stops the checklist
Close out Closing a failed checklist once its failed items have been dealt with. It then counts as passed

Progress shows trades down the side and levels across, grouped by building, lowest level first. Each cell is one trade on one level: a number such as 3/8 is passed out of required, and a single place shows its state in words. The cell is marked Not started, In progress, Passed or Failed, and the legend under the grid says which is which. The totals across the top count every required inspection on the project.

A trade done for each building shows in a Whole building column, and one done once for the project in a Whole project column. With two or more buildings you can show one building at a time.

When a trade’s hold point is waiting and the plan says which programme task it holds up, a list Hold points waiting on the programme above the grid says so, soonest task first: for example “Hold point waiting, Tiling Level 2 starts in 3 days”.

  1. Mark hold and witness points on a checklist
  2. Set up the inspection plan for a project
  3. Do an inspection from the ITPs
  4. Print the ITP register for a trade