Enter the labour a project needs

Say how many people of each trade a project needs each week. Workforce Planning then shows who is assigned against it, where you are short, and who is free to fill the gap.

  • Who can do this: “Enter labour demand”, and you must be able to change the project. Administrators always can, on the projects they have access to.
  • The trades and roles exist. If there are none, the Demand tab sends you to Crews and roles to add them.
  1. Open Workforce Planning and choose the Demand tab.
  2. Choose Add a need.
  3. Choose the Project and the Trade or role.
  4. Type People needed. Halves are allowed, such as 1.5.
  5. Choose the First week and type how many Weeks.
  6. Check the line under the form, for example “Harbour Lane Apartments needs 4 people as Carpenter for 6 weeks”. Choose Add need.
  7. The project and trade appear in the grid. Each week shows the number needed, how many are assigned underneath, and Short with the gap where fewer are assigned.
  8. To change one week, type the new number straight into its box and press Enter or click away. An empty box or 0 means none needed.
  1. Choose the Next month tab.
  2. Whole company shows each trade, week by week: needed, assigned and free. Covered means enough are assigned; Short 2, can be covered means enough people are free to fill it; Short 2, only 1 free means they are not.
  3. Below, each project shows its needs and Who is available: the free people of that trade, and for how many of the weeks.
  4. Assign them on the Board. See Assign people to a project.
  • Adding a need replaces any number already in those weeks for that project and trade.
  • Assigned is counted by share of time: two people full time and one half time is 2.5.
  • Next month is the weeks whose Monday falls in the next calendar month.
  • Someone free but with an expired ticket is marked Ticket expired in Who is available. They still count as free, but cannot be assigned without an override.
  • Needs are typed in; they are not taken from the programme or the estimate.