Set up the head contract
Before the first claim goes to the client, enter the facts of the contract: the contract sum, the date for practical completion, the retention terms and any liquidated damages. Every figure on the Head Contract page, and every claim against the schedule of values, works from these.
Before you start
Section titled “Before you start”- Who can do this: anyone with Set up the head contract and schedule of values, for the whole company or through their role on the project. Administrators always can.
- Have the contract in front of you. Amounts are ex GST.
-
Choose the project in the left-hand picker, then open Head Contract from the menu on the left. The Contract tab opens.
-
Choose Set up the contract. If the contract is already set up, choose Edit instead.
-
Check the Contract sum. If the project has one priced estimate, the box already holds its contract price, converted to ex GST, and says so underneath. If it has several, each is offered as a button under Start from an estimate’s contract price: choose the right one, or type the sum.
-
Type the Contract number if the contract has one.
-
Enter the Date for practical completion: the date written in the contract, before any extension of time.
-
Under Extensions counted in, choose Working days or Calendar days, as the contract says.
-
If the client holds retention, switch on The client holds retention and fill in:
- Held from each claim: the percentage, for example 5%.
- Up to: the limit, as a percentage of the contract sum. 0 means no limit.
- Released at completion: the share handed back at practical completion. The rest comes back after the defects period.
- Defects period, in months.
A sentence under the fields says what these terms will do, for example “5% is held from each claim, until $142,500 is held. Half comes back at practical completion and the rest 12 months later, at the end of the defects period.”
-
If the contract has liquidated damages, switch on Liquidated damages apply and enter the amount For each day late.
-
Under Claims to the client are made, choose By payment stage (as Progress Claims has always worked) or Against the schedule of values. For the second, choose On which estimate if the project has more than one.
-
Choose Save. The figures across the top of the page fill in.
What happens next
Section titled “What happens next”- Enter the lines of the contract on the Schedule of values tab: see Enter the schedule of values.
- When the work reaches practical completion, choose Edit and fill in Practical completion reached. Days late stop counting on that day, and retention can be released on the next claim.
Good to know
Section titled “Good to know”- The way claims are made is fixed once a claim against the schedule of values exists. The form then says so and does not offer the choice.
- An estimate that already has claims by payment stage is not offered for claims against the schedule of values. The two kinds are never mixed on one estimate.
- Working days are Monday to Friday, less the company’s holidays.
- Days late are calendar days from the moved date for practical completion to the day it was reached, or to today if it has not been. Liquidated damages are those days times the daily amount.
- An amount box keeps what you typed if it is wrong and says why underneath, such as “Amounts cannot be negative.”
- Nothing on this page sends an email or a notice to the client.