Do an inspection from the ITPs

When a trade has finished a unit or a level, start its inspection from the grid. The checklist opens with the place already filled in, and when it is completed the grid shows the result.

  • Who can do this: starting and filling in needs “Fill in checklists” on the project. Releasing a hold point, signing and pressing Complete need “Sign off a checklist”. Administrators hold both.
  • The trade is in the project’s plan.
  1. Open Quality, choose the project on the left, then the ITPs tab. Progress shows the grid.
  2. Click the cell for the trade and the level, for example Waterproofing on Level 5. A window lists the places in it, each with its state.
  3. Press Start beside the place, for example Unit 501. The checklist opens in the same page, with the unit under Building or unit.
  4. Answer each item Pass, Fail or N/A. Add a note or a photo where it helps. Press Save to keep your answers as you go.
  5. On an item marked “hold point” that you passed, press Release hold point. Type who released it in Released by, their Company, and press Release. The item now reads “Released by” with the name and the time.
  6. On a witness point, press Record witness if someone witnessed it. This is optional.
  7. If the checklist must be signed, press Sign under Signatures, fill in Name, Company and Signing as, and press Sign.
  8. Press Complete. The checklist is Passed, or Failed if any item failed. If something is missing, a red box under the toolbar lists it, for example “Hold point not released: Membrane cured before tiling”.
  9. Press All checklists to go back. The grid’s cell shows the new count.

The cell counts the unit as passed or failed. When every place in a cell has passed, the cell is marked Passed: the trade has passed that level.

  • A failed item can raise a defect. Press Raise defect on it; the defect is created in Defects at the same building, level or unit.
  • A failed inspection can be done again. The cell’s window offers Inspect again for that place. The latest inspection decides the cell.
  • A failed checklist can be closed out once the failed items have been dealt with: open it and press Close out. It then counts as passed.
  • Starting a place that already has an inspection in progress opens that one instead of starting a second.
  • Open in the cell’s window opens an inspection already started.
  • The release records the time with your login, whoever’s name you type.
  • The phone app fills in the same checklists, but does not show hold points and does not stop completion on one not released.