Price daywork into a variation

Signed daywork sheets are claimed by turning them into a variation: a client variation for the client’s sheets, or a variation on the subcontract for a subcontractor’s sheets. Several sheets can go on one variation.

  • Who can do this: “Price daywork into variations”, and for a client variation also “Edit variations” and access to the estimate; for a subcontract variation also “Create and edit subcontract variations”.
  • The sheets are signed by both sides, and approved where your workflow asks for it.
  1. Open Daywork Sheets and choose Price into a variation. Tick boxes appear beside the sheets that can be priced.

    The register with Price into a variation on: a tick box beside each sheet that can be priced, the line saying one sheet ticked for the client, and Price 1 sheet

  2. Tick the sheets. Once you tick one, only sheets that go with it can be ticked: all for the client, or all on the same subcontract. The line above says how many are ticked and their total.

  3. Choose Price with the number of sheets. A window lists each sheet with its cost, its overheads and profit, and its total.

    The Price into a client variation window: the sheet with its cost, overheads and profit and total, the variation name, and Create the variation

  4. For a client variation: check the Variation name (it starts as “Daywork” and the sheet numbers) and, when the project has more than one estimate, choose the Estimate.

  5. For a subcontract variation: check the Title, choose the Cost code, and optionally choose under Paid for by the client variation that pays for this work.

  6. Read the sentence at the bottom, for example “Creates a client variation for $2,908.05 ex GST from 2 daywork sheets”, and choose Create the variation (or Create the subcontract variation).

  7. A line says what was made, with a button to open it.

  • A client variation is a draft in Variations, with one line per sheet: the sheet’s cost as the line’s cost, its overheads and profit as the markup, and GST added as the variation adds it. It then follows the Variations module: internal sign-off where you have one, then sent to the client from Variations.
  • A subcontract variation is a draft addition on that subcontract, its description listing the sheets. It is sent for approval in Subcontracts like any subcontract variation.
  • Each sheet now shows On and the variation’s name, with a link to it.
  • In Variations, do not use Update all prices on a variation made from daywork: it would work the daywork lines out again from items they do not have, and set them to $0.
  • A sheet can be on one live variation only. If that variation is deleted, the sheet says “its variation was deleted” and can be priced again.
  • A sheet on a live variation cannot be reopened.